Worked example
Downtown Vancouver — Heating System Upgrade. We replaced aging boiler equipment with a Rinnai RCB750 boiler and two Rinnai Demand Duo tankless water heaters, plus new piping, electrical, insulation and a 4″ CPVC exhaust system — all to current Vancouver code. Working directly with Rinnai on commissioning, what was scoped as a four-week job was completed in two, and Technical Safety BC passed the installation on the first inspection.
What’s included
Class A gas scope for high-input equipment, coordination with Technical Safety BC, engineering and permits where required, minimally disruptive staging for occupied buildings, full commissioning and documentation.